Building 630 Gantry Tower Stabilisation

CLIENT

Spotless / Department of Defence

SERVICE INDUSTRY

Defence

PROJECT LOCATION

Amberley, QLD

STATUS

Completed 4 November, 2020

VALUE

$60k
Gantry-Tower-Stabilisation-B-Finished

SCOPE OF WORK

The scope included the following: Supply & Install six screw piles for guide wires, supply and install 12 guide wires tensioned as per engineer’s specification, treat corrosion around base plates with an approved system, supply and install 200mm concrete slab to each tower base, and provide adequate fencing to new exclusion zone complete with a double gate and signage.

INNOVATION

​Screw Piles were utilised over traditional concrete piles as it was a cost & time effective means which provided excellent pull out resistance.