14 Dam Fill Point Slab Replacement
CLIENT
Anglo Coal (Dawson Management) Pty Ltd
SERVICE INDUSTRY
Mining | Heavy Industrial
PROJECT LOCATION
Moura, QLD
STATUS
Completed 26 June, 2020
VALUE
$450k
SCOPE OF WORK
Replaced the concrete slab at the '14 Dam Fill Point' at the Site. The slab was required to support the water trucks and the fill infrastructure and facilitate proper drainage. This included the demolition of existing concrete slabs (and removal of spoil and disposal of old slab materials), new slab foundation preparation works, construction of new reinforced slab, all necessary quality assurance, quality control and testing of the Materials and the completed works.
INNOVATION
n/a